Monoline Constructions offers complete grey structure construction services on a turnkey basis, including labor, materials, site supervision, and execution according to approved drawings and construction standards.
The client must provide clear and uninterrupted possession of the plot before construction begins.
All architectural drawings, structural details, specifications, and required approvals should be finalized and shared prior to the start of work to avoid delays or additional costs.
Water and electricity required during construction shall be arranged by the client. Any utility bills during the project duration will also be the responsibility of the client.
The construction site should be clean and accessible. In case of debris removal, leveling, or additional preparation work, related expenses will be charged separately.
If the project location has restricted access for heavy vehicles or construction material transportation, additional handling or shifting charges may apply.
Any laboratory testing, soil testing, or material testing requested by the client or required by authorities shall be paid by the client.
Monoline Constructions will execute all work according to approved drawings and agreed specifications.
Our team will assist the client regarding construction guidance, technical coordination, and related documentation throughout the project.
If any work is found inconsistent with approved specifications, it will be corrected by the company without additional labor charges.
Excavation and foundation work will be completed according to structural engineering drawings.
Approved anti-termite treatment chemicals will be applied in foundation areas for long-term protection.
Plain cement concrete (PCC) and foundation filling will be completed as per engineering standards.
If excavation depth exceeds the standard agreed level, additional excavation and filling costs will apply.
Grade-60 steel reinforcement bars will be used according to structural design requirements.
Approved A+ quality bricks and premium-grade cement brands will be utilized depending on market availability.
Sargodha plant crush and recommended sand will be used for RCC and masonry works.
Waterproof membrane treatment will be applied in damp-proof course areas where required.
Steel quantity shall be according to structural requirements for standard residential construction. Any extraordinary structural demand or additional steel consumption beyond standard limits shall be charged separately.
Roof treatment includes proper slope formation for rainwater drainage along with waterproofing application.
Rainwater drainage pipes and khurras will be installed according to site requirements.
Parapet wall RCC work, decorative roofing elements, or additional rooftop structures will be considered extra work unless specifically included in the agreement.
High-quality UPVC and PPRC piping systems will be installed for water supply and drainage works.
Separate hot and cold water lines will be provided in washrooms and kitchens where applicable.
Sewerage lines, rainwater pipes, and underground drainage systems will be completed according to approved plumbing layouts.
Additional plumbing points or revisions requested after execution may result in additional charges.
Electrical conduit piping will be installed inside slabs and walls before plaster work.
Standard provisions include points for lights, fans, switches, sockets, and chandeliers according to approved electrical layouts.
Any additional electrical points requested after plaster completion shall be charged separately.
External electrical fixtures outside covered areas may also incur extra costs.
Gas piping provisions will be provided for the kitchen and geyser points as per approved layout.
Additional gas points requested after completion of wall plaster may be charged separately.
Any design modification, additional construction, structural change, or revision requested during construction will be treated as variation work and charged separately.
Special architectural elements such as Spanish elevations, decorative moldings, pergolas, landscaping features, BBQ counters, fireplaces, swimming pools, or lift areas are not included in standard grey structure rates unless specifically mentioned.
Corner plots, increased floor heights, steel shuttering requirements, or non-standard structural designs may result in additional charges.
Construction timelines may vary depending on weather conditions, site conditions, material availability, governmental approvals, or client-side delays.
All government fees, society approvals, taxes, NOCs, and regulatory charges shall be the responsibility of the client.
Security arrangements, watchman salaries, and utility connections required during construction shall be managed by the client.
Any modification requested after completion of executed work may involve demolition, reconstruction, additional labor, and material costs.
Such changes will be billed according to actual site expenses and revised construction requirements.
The expected completion period for standard grey structure construction is approximately 3 to 4 months depending on project size, weather, and site conditions.
Construction timelines may be adjusted through mutual agreement between both parties.
Monoline Constructions shall not be held responsible for delays caused by factors beyond reasonable control, including:
In such situations, project completion timelines may be reasonably extended.
Payments shall be made according to the mutually agreed installment schedule.
The company will notify the client before each payment milestone.
Delayed payments may affect construction progress and project delivery timelines.






If construction material prices or labor costs increase significantly due to market fluctuations or inflation, revised rates may apply for the remaining work.
Transparent pricing structure designed to help clients understand construction costs, installment plans, and project budgeting before work begins.
Per Square Foot
Estimated Covered Area
Approximate Grey Structure Cost
Before Excavation Work
After Foundation Completion
7 Feet Masonry Completion
After First Lenter Completion
After Second Lenter Completion
Internal Plaster & Services
Water Tank & Outer Plaster
Roof & Floor Kacha Work
Project Handover
Final construction cost may vary depending on plot condition, design complexity, market material rates, excavation depth, and additional structural or architectural requirements requested by the client.